Online cladding and reinforcement of 14' of H2S Flare Line (30" - 48" dia.) with ¾" thick plate.
Develop a procedure to do the cladding without shutting down the unit. Build an in-house mock up to ensure that the final quality of the Liburdi engineered process would achieve the desired results. Liburdi’s Boilermakers/UA were responsible for all of the rigging, fitting and seal welding of the plates, reinforcing pads and flanges.
Liburdi’s engineering staff successfully implemented a plan to accomplish the unique task of doing this project while the unit was online. The procedure, along with the highly skilled tradesmen, were able to complete the task as they had practiced it on the mock-up to complete the desired results